Citywide project · City streets
Street Repaving and Rebuilds
Repaving happens every year. Big rebuilds: West Lisbon Avenue finishes in fall 2026, and West National Avenue runs through 2028. The 2027 budget proposes a record $19.2 million for local streets.
The project as a whole
Under construction now.
Every year the City of Milwaukee repaves or rebuilds some of its streets. The Department of Public Works picks the streets, and the Common Council approves the money in batches. About a quarter of city streets were rated in poor condition in 2022, and fixing all of them would cost about $821 million. Some streets get a full rebuild that can change their whole layout, like West Lisbon and West National avenues.
Latest
The map
Map key
Street Repaving and Rebuilds
- City street paving projects
- City alley projects
- Alder district borders
City street paving and alley projects from the Department of Public Works projects map. The line pattern shows each project's stage: solid is finished, short stripes are being built, dashed is designed or waiting for construction. This map is not made or endorsed by the city. Tap any line to see that spot in Google Street View.
By the numbers
- lane miles of streets the city is responsible for
- 4,600+
- lane miles of streets the city is responsible for
- Urban Milwaukee, September 20, 2026
- of city street lane miles in poor condition (2022 survey)
- About 25%
- of city street lane miles in poor condition (2022 survey)
- DPW memo, May 30, 2025
- to bring every poor street up to good condition
- $821 million
- to bring every poor street up to good condition
- DPW memo, May 30, 2025
- resurfaced each year in the High Impact paving program
- 13 to 15 miles
- resurfaced each year in the High Impact paving program
- City of Milwaukee, 5th District
- rebuilt each year with city budget money
- About 4 miles
- rebuilt each year with city budget money
- City of Milwaukee, 5th District
- for local streets in the mayor's proposed 2027 budget, a record
- $19.2 million
- for local streets in the mayor's proposed 2027 budget, a record
- Urban Milwaukee, September 20, 2026
The story
The City of Milwaukee is responsible for more than 4,600 lane miles of streets. A 2022 survey rated about a quarter of them in poor condition, and most of those are quiet neighborhood streets. The Department of Public Works (DPW) estimates it would cost about $821 million to bring every poor street up to good condition.
How streets are chosen. DPW rates every street's surface, and it re-checks the whole city about every eight years. It also looks at what crews see in the field and what residents report.
Two kinds of work. The cheaper fix, called High Impact paving, puts a new layer of asphalt on top of the old street. It costs about one-third as much as rebuilding, and it covers about 13 to 15 miles a year. For this program the city usually picks busy connecting streets and streets in shopping areas, so the most drivers benefit. A full rebuild tears out the old street. The city budget pays for rebuilding about 4 miles a year.
How it is paid for. Busy main streets often get state and federal aid. Neighborhood streets mostly do not, so the city pays for them from its capital budget, the part of the budget for building and fixing things. The city also gets help from a $30 vehicle registration fee and a small state grant. Until 2008, owners of houses along a street were charged for part of its repaving. The city replaced those charges with the vehicle fee. Owners still pay part of some work, like rebuilding the alley behind their homes.
How the votes work. Each year the Common Council votes on batches of projects. On SHIFT MKE, files that start engineering are titled "Plans street repairs at many locations," and files that approve construction are titled "Approves street repairs at many locations." Each batch can also include sewer, sidewalk, and other work. Files marked "owners pay part" include work that neighbors are charged for, and those get a public hearing first.
The big rebuilds. Some streets get more than new pavement. When a street is torn out and rebuilt, its whole layout can change: the number of lanes, bike lanes, crossings, and trees. These are the biggest ones now:
West Lisbon Avenue. 2.1 miles from North 100th Street to West Burleigh Street. The road goes from four lanes to two, with raised bike lanes separated from traffic and roundabouts at 84th and 92nd streets. Construction began in April 2025 and should finish in fall 2026. Federal money pays 80 percent and the city pays the rest.
West National Avenue. From South 1st Street to South 39th Street, rebuilt in three phases: 27th to 39th in 2026, 1st to 11th in 2027, and the part in between in 2028. It gets raised bike lanes and costs about $50 million. National Avenue is also state highway WIS 59, so the state is involved.
6th Street Next. A plan to redesign 2.6 miles of 6th Street, from National Avenue to North Avenue, possibly with raised, protected bike lanes. The city won a $36.56 million federal grant in 2024, but most of it was taken back in July 2025 under H.R. 1, a federal budget law. A separate $2.1 million federal agreement still pays for early design. No construction date is set.
WIS 175. A six-lane freeway spur between Wisconsin Avenue and Lisbon Avenue, built in 1962. From 2022 to 2025, WisDOT, Milwaukee County, and the city studied four options: rebuild it as it is, or end it near the north, middle, or south of the corridor and use city streets for the rest. The final report, dated October 24, 2025, did not choose one.
Timeline
- 2008 · DoneCity drops paving charges to neighbors, adds a $20 vehicle fee
- 2013 · DoneHigh Impact paving program starts
- 2021 · DoneVehicle registration fee rises to $30
- Apr. 2025 · DoneWest Lisbon Avenue rebuild starts
- June 2025 · DoneDPW report: $821 million to fix all poor streets
- July 2025 · DoneMost of the 6th Street grant taken back
- Oct. 2025 · DoneWIS 175 study ends without choosing an option
- 2026 · UnderwayWest National Avenue rebuild, 27th to 39th streets
- Sept. 2026 · DoneMayor proposes $19.2 million for local streets
- Fall 2026 · UnderwayWest Lisbon Avenue rebuild finishes
- Nov. 2026 · UnderwayCommon Council votes on the 2027 budget
- Spring to fall 2027 · Planned2027 construction season
- 2027 to 2028 · PlannedWest National Avenue rebuild, 1st to 27th streets
- Years
- Every year, spring to fall. Big rebuilds: 2025 to 2028.
The money
- About $60 million a year: Spent on city streets each year, on average, 2022 to 2025Paid by: mix not published. Source, May 30, 2025 ↗
- About $821 million: To bring every street rated poor up to good conditionPaid by: not funded. Source, May 30, 2025 ↗
- $19.2 million: Local street paving in the mayor's proposed 2027 budget, a recordPaid by: city. Source, September 20, 2026 ↗
- 80 percent: West Lisbon Avenue: Construction share, up to the federal cost capPaid by: federal. Source, November 4, 2026 ↗
- 20 percent: West Lisbon Avenue: Construction share, plus anything above the federal capPaid by: city. Source, November 4, 2026 ↗
- assessed to property owners: West Lisbon Avenue: Sidewalk and driveway approach replacementPaid by: private (property owners). Source, November 4, 2026 ↗
- about $50 million: West National Avenue: Whole rebuild, 1st Street to 39th StreetPaid by: not broken down. Source, April 8, 2026 ↗
- $25 million: West National Avenue: Federal funds allocated to the rebuildPaid by: federal. Source ↗
- $36.56 million: 6th Street Next: Neighborhood Access and Equity grant for design and construction (awarded spring 2024)Paid by: federal; most rescinded July 2025 under H.R. 1. Source, November 4, 2026 ↗
- $2.1 million: 6th Street Next: Grant agreement still in place for early engineering and environmental approvalPaid by: federal (USDOT). Source, November 4, 2026 ↗
Yearly repaving is paid mostly from the city's capital budget. Each big rebuild has its own mix of federal, state, and city money. The city publishes no total for Lisbon Avenue, National Avenue's cost comes from news reports, and the WIS 175 study lists no costs.
Designs, renderings, and plans
What it could look like, from the agencies’ own drawings, renderings, and meeting boards. Each link opens their file.
- Design drawingWest Lisbon Avenue: Public meeting 4 roll plot The final layout drawn on an aerial photo, including the roundabouts at 84th and 92nd streets and the raised bike lanes.City of Milwaukee, March 19, 2024
- Design drawingWest National Avenue: Cross-section: 39th Street to 33rd Street A slice of the new street showing lanes, raised bike lanes, and sidewalks.City of Milwaukee
- Design drawingWest National Avenue: Cross-section: 33rd Street to 13th Street The middle section, where the street drops from four driving lanes.City of Milwaukee
- Design drawingWest National Avenue: Cross-section: 13th Street to 1st Street The eastern section near Walker's Point.City of Milwaukee
- Design drawingWest National Avenue: Roll plot: 39th Street to 27th Street The 2026 phase drawn on an aerial photo (three more roll plots cover the rest).City of Milwaukee
- Design drawing6th Street Next: Public meeting 2 roll plots The design options drawn on aerial photos of the street.City of Milwaukee, Spring 2026
- Design drawing6th Street Next: Option: two-way protected bike lane with median (Florida Street to Clybourn) A cross-section of one option for the Walker's Point segment.City of Milwaukee, Fall 2025
- Design drawing6th Street Next: Option: center-running transit and protected bike lanes (Clybourn to McKinley) A cross-section with bus lanes in the middle of the street downtown.City of Milwaukee, Fall 2025
- Design drawing6th Street Next: Option: protected bike lanes (McKinley to North Avenue) A cross-section of the northern segment.City of Milwaukee, Fall 2025
- MapWest Lisbon Avenue: Project limits map The 2.1-mile stretch from 100th Street to Burleigh Street.City of Milwaukee
- Map6th Street Next: Project area map The 2.6-mile corridor from National Avenue to North Avenue.City of Milwaukee, 2023 (from file name)
- MapWIS 175: Study area map The freeway spur from Wisconsin Avenue to Lisbon Avenue.WisDOT
- Meeting boardsWest Lisbon Avenue: 2026 construction staging display Which side of the street is closed during each stage of 2026 work.City of Milwaukee, 2026
- Meeting boardsWest National Avenue: Public meeting 3 boards The recommended design shown to the public.City of Milwaukee, June 7, 2023
- Meeting boardsWest National Avenue: 2026 construction overview The three construction phases and what closes when.City of Milwaukee, 2026
- Meeting boards6th Street Next: Public meeting 2 boards, part 1 The design options shown at the second public meeting (part 2 and Spanish versions are on the project page).City of Milwaukee, Spring 2026
- Meeting boards6th Street Next: Public meeting 1 slide deck The virtual meeting slides introducing the project.City of Milwaukee, October 22, 2025
- Meeting boardsWIS 175: Past public meeting materials Boards and maps shown at earlier public meetings.WisDOT (hosted by GRAEF), 2022 to 2025
- Study or reportWIS 175: Reimagining WIS 175 final report The four options studied, from rebuilding the freeway to ending it and using city streets.WisDOT, October 24, 2025
- Study or reportWIS 175: Final report appendices Supporting traffic data and public comments.WisDOT, 2025
- Project pageWest Lisbon Avenue: Lisbon Avenue project page Schedule, monthly updates, and all meeting materials since 2021.City of Milwaukee, Checked November 4, 2026
- Project pageWest Lisbon Avenue: Project overview (PDF) A short summary of what is being built.City of Milwaukee
- Project pageWest National Avenue: National Avenue project page Cross-sections, roll plots, meeting boards, and monthly updates.City of Milwaukee, Checked November 4, 2026
- Project pageWest National Avenue: WisDOT WIS 59 National Avenue page The state's summary of the project limits and schedule.WisDOT, Checked November 4, 2026
- Project page6th Street Next: 6th Street Next project page All cross-section options for the four segments, meeting boards, and the project map.City of Milwaukee, Checked November 4, 2026
- Project pageWIS 175: WisDOT study page Summary and links to the report.WisDOT, Checked November 4, 2026
In the news
Recent stories from local news sites, public radio and TV, and advocacy groups (labeled), found through Google News and updated every morning. Headlines link to the outlet.
Who decides, and how to have a say
City of Milwaukee. The Department of Public Works chooses and designs the projects, and the mayor proposes the budget. The Common Council approves the budget and votes on each batch of street projects. Some city streets are also state highways, like National Avenue (WIS 59), so the state (WisDOT) shares those decisions. Freeways belong to the state; the one listed here, WIS 175, is a state study of turning part of it into city streets.
Sources, checked November 4, 2026: City of Milwaukee DPW, Projects page (what counts as street paving, projects map); City of Milwaukee DPW, High Impact Paving Program (started 2013, cost about one-third of rebuilding); City of Milwaukee 5th District, The Process Behind Road Construction (how streets are chosen, miles per year, alley costs); City of Milwaukee DPW, memo on pavement quality, May 30, 2025, with press release of June 18, 2025 (condition, $821 million, funding sources); City of Milwaukee DPW, Special Assessments (charges to property owners); Urban Milwaukee, June 23, 2025 (2008 switch from assessments to a vehicle fee); Urban Milwaukee, September 20, 2026 (2027 budget proposal, lane miles); Common Council file 260864, vote November 4, 2026 (example of a 'plans street repairs' file); Common Council file 260758, adopted October 13, 2026 (example of an 'approves street repairs' file); City of Milwaukee DPW projects map data; Urban Milwaukee, April 8, 2026 (National Avenue phases, cost); FOX6, April 8, 2026 (National Avenue raised bike lanes); City of Milwaukee, Lisbon Avenue project; CBS 58 (Lisbon Avenue groundbreaking); City of Milwaukee, 6th Street project; Urban Milwaukee, March 12, 2024 (6th Street grant); WisDOT, Reimagining WIS 175 study page; WIS 175 final report, October 24, 2025; map: City of Milwaukee DPW projects map. Street View imagery © Google.